Richmond Hill Rd upgrade reflects commitment to safety
Lismore City Council’s road crews are currently engaged in the reconstruction of a 560-metre segment of road between Roy Place and Laihaina Crescent. This project is part of the Council’s ongoing commitment to enhancing the safety and quality of Lismore’s local road network.
The Richmond Hill Road upgrade, which began in September 2023, has already seen the successful reconstruction of a 1.8km section, significantly improving both safety and the longevity of the roadway.
Mayor Steve Krieg announced that the final phase of the Richmond Hill Road reconstruction will extend from the current endpoint to approximately 300 metres beyond the Laihaina Crescent intersection.
“This phase is in its final planning stages and is expected to employ the same methodologies and treatments as previous stages. Upon completion, the total length of reconstructed road will reach 2.7km,” Mayor Krieg stated.
In early June, work commenced on removing the old road surface over the 560-metre stretch. This was followed by in-situ stabilisation of the lower sub-base pavement layer, which involves incorporating a binder to enhance the performance characteristics of the sub-base, allowing for the reuse of existing materials in the new pavement design.
The stabilisation process uses a large reclaimer machine to mix the existing pavement material with the binder to the required depth. This mixture is then compacted and shaped to achieve the necessary geometry. A new base layer is subsequently laid and compacted to the finished surface height.
Additionally, the project includes adjustments to adjoining driveways, which may involve replacing pipe crossings and installing grates or concrete dish drains for improved stormwater management.
Mayor Krieg emphasised that the Richmond Hill Road reconstruction aims to enhance the road’s structural integrity, geometry, stormwater infrastructure, and overall ride quality. He acknowledged the challenges faced by regional councils in maintaining local road networks.
“Lismore City Council is responsible for 1215km of sealed and unsealed roads within our LGA. The extensive investment needed for such reconstructions and repairs would be unattainable without the continued funding support from our State and Federal partners,” he said.
The Richmond Hill Road project is jointly funded by the State Government’s Regional and Local Roads Repair Program and Fixing Local Roads Program, along with Lismore City Council.
For updates on the Richmond Hill Road upgrade, visit Council’s Your Say page at Lismore Your Say.
For more local Lismore news, click here.